Russia is planning a 15.58-billion-ruble underground data centre in Omsk, with capacity for 4,200 server racks and a 100 MW heat recovery system. The unusual project aims to turn server waste heat into energy for a business center, hotel, and aquapark while creating a protected hub for AI computing.

Must Read

Frontier India News Network
Frontier India News Networkhttps://frontierindia.com/
Frontier India News Network is the in-house news collection and distribution agency.

Russia intends to build an underground data center in Omsk that will integrate high-density computing infrastructure, physical protection, and large-scale thermal recovery.

An Underground Data Centre Designed for AI Computing

The G-System project is a data center construction approach that involves placing critical computing infrastructure beneath the earth, rather than in traditional above-ground buildings. The proposed facility will be located within a reinforced monolithic structure situated deep underground.

The envisioned capacity is approximately 4,200 high-density server racks. These racks are designed to accommodate high-demanding computing workloads, such as artificial intelligence applications that necessitate sophisticated cooling infrastructure, high-performance servers, and substantial processing capacity.

AI computing has increased the importance of data center infrastructure. Modern AI duties necessitate the continuous operation of clusters of processors and accelerators, which generates significant heat and electricity demand. Therefore, data center operators must satisfy two interrelated prerequisites: the efficient removal of heat and the provision of adequate electrical power.

Through an energy recovery arrangement and an integrated underground facility, G-System endeavors to satisfy both requirements. Nevertheless, the developer has not disclosed the exact setup of the computing infrastructure, detailed equipment specifications, or the complete engineering documentation to the public.

A 160-Meter Business Center Above the Data Center

The underground computing facility will form part of a larger multifunctional development incorporating the Prince business center. The data center will connect to the above-ground building via a shared energy and environmental infrastructure, with the latter expected to reach a height of approximately 160 meters.

The idea is to operate the underground and above-ground facilities as a unified system, rather than as separate properties. The data center will produce heat as a result of its computing operations, while the structures above it will supply consumers with the recovered energy.

An aquapark will be included in the proposed complex, in addition to business, hospitality, and educational facilities. The recovered heat is intended to maintain the temperature of the aquapark’s water and support space heating in the hotel and other buildings.

100 MW Heat Recovery: Turning Server Heat Into Useful Energy

The most significant engineering feature of G-System is its proposed heat recovery system, with a stated capacity of up to 100 MW. The system is intended to redirect thermal energy generated by operating servers to heating applications throughout the multifunctional complex.

Data centers require electricity to operate processors, storage systems, networking equipment, and cooling infrastructure. Ultimately, a significant portion of the electrical energy converts to heat. The G-System specifies that the data center be integrated with buildings that have continuous heating requirements, rather than cooling, to maximize the use of this thermal output.

The hotel’s heating system, the business and educational centers, and the aquapark’s water-heating infrastructure are planned to be supplied by the recovered heat. The aquapark is a critical element due to the necessity of a consistent supply of thermal energy to maintain water temperatures.

According to the developer, this integrated arrangement has the potential to decrease operating expenditures by approximately 70%. Additionally, it anticipates that the complex will recoup its investment within 5.5 years.

Underground Construction and Physical Protection

Another critical component of the proposal is the underground placement of the G-System. Banking, telecommunications, government services, industrial operations, and other digital systems are all supported by data centers. Consequently, their accessibility is a critical component of the nation’s infrastructure.

Computing equipment is to be positioned within a deep subterranean monolithic structure to offer addition physical protection against external threats and specific environmental disturbances. Depending on their depth, structural design, access arrangements, and supporting infrastructure, these facilities have the potential to provide more protection than conventional buildings.

Nevertheless, the engineering challenges associated with underground construction are unique. These encompass the management of groundwater, ventilation, fire suppression, emergency access, power distribution, and the removal of heat from densely packed server equipment. It is crucial to ensure that the ventilation system is consistently reliable, as the facility is anticipated to accommodate high-density computing.

Russia’s Wider Interest in Underground Data Centers

The Omsk proposal comes amid growing interest in protecting Russia’s digital infrastructure against physical disruption. The continuous availability of computing facilities is becoming increasingly critical to the operation of telecommunications networks, industrial control systems, and digital services.

In a separate development reported in November 2026, Rostelecom was reportedly discussing the creation of underground data center facilities with mining and metals company Nornickel. If main facilities are damaged, the proposed infrastructure would offer secure fallback locations for the restoration of digital services.

The strategy encompasses various resilience levels. The initial step involves preserving backup copies of data in distinct locations. The second involves the distribution of computing resources and services across facilities that are geographically separated. The third method involves the implementation of subsurface infrastructure to offer supplementary physical protection.

Rostelecom’s discussions with Nornickel are separate from the G-System development in Omsk.

Investment, Implementation, and Expansion Plans

The Omsk complex is expected to require an investment of 15.58 billion rubles. MeGa Plast has successfully completed the critical stage of preliminary investment design and is currently in the process of formalizing the development through legal means. Additionally, the organization is assembling a consortium of strategic investors to facilitate implementation.

It is expected that the data center and the Prince business complex will be organized through distinct corporate structures. This would allow the two components to be developed and financed as interconnected but distinct infrastructure assets.

MeGa Plast intends to use G-System as a pilot project and subsequently replicate the concept in other Russian cities with populations exceeding one million. The model could be adapted to locations where the demand for computing capacity is in alignment with the potential to use recovered thermal energy if it is effectively implemented.